How Baiterek Holding’s subsidiaries support green projects
(as of December 1, 2021)
Read more
Project description: Construction of the Abai wind farm with a capacity of 150 MW in East Kazakhstan region and Almaty region
Commissioning: December 2022
Total cost of the project: 84.9 billion tenge
The amount of the Holding's participation: 56.9 billion tenge
Project description: Construction of small hydroelectric power plants in Almaty region
Commissioning: April 2023 (planned)
Total cost of the project: 12.3 billion tenge
The amount of the Holding's participation: 3.8 billion tenge
Project description: Construction of the Ybyray wind farm with a capacity of 50 MW in Kostanay district of Kostanay region
Commissioning: May 2022
Total cost of the project: 27.1 billion tenge
The amount of the Holding's participation: 16.9 billion tenge
Project description: Construction of a 50 MW solar power plant in Almaty region
Commissioning: December 2020
Total cost of the project: 13.4 billion tenge
The amount of the Holding's participation: 10.7 billion tenge
Description: Construction of "SPP" Baikonyr "in the Kyzylorda region, with a capacity of 50 MW
Commissioning: March 2020
Total project cost: 27 billion tenge
Holding participation amount: 4.2 billion tenge
Description: Construction of a solar power station "Kengir" in the Karaganda region, with a capacity of 10 MW
Commissioning: Jan. Feb 2020
Total project cost: 25.3 billion tenge
Holding participation amount: 18.5 billion tenge
Description: Renovation of the bus fleet of Pavlodar city (electric city buses)
Commissioning: July 2019
Total project cost: 2.2 billion tenge
Holding participation amount: 1.9 billion tenge
Description: Construction of a solar power plant in the Mangistau region, with a capacity of 2 MW
Commissioning: May 2020
Total project cost: 1.2 billion tenge
Holding participation amount: 0.96 billion tenge
Description: Purchase of 100 units of City Bus 4 electric city buses
Commissioning: Aug. Feb 2020
Total project cost: 14.6 billion tenge
Holding participation amount: 11.7 billion tenge